MASTERIMPACT® - Installation
|
|
|
|
|
|
|
 |
|
|
|
|
-
Install standard steel stud partition framing, studs at nominal 300mm centres vertical and 2440mm
centres horizontal.
|
-
Fix MASTERIMPACT® board to one face
only, install all internal pipes and cables.
|
-
Fix MASTERIMPACT® board to the
front face, drill holes between each vertical stud, and at nominal 1220mm height centres.
|
|
|
|
|
|
|
-
Insert the filler hose and begin to pump the cement mixture into the cavity, ensuring all
apertures are fully filled.
|
-
Leave to dry for 48 hours, then apply joint filler where appropriate to fill holes and gaps
between boards etc.
|
-
Where a superior finish is required, apply a skin coat of gypsum plaster over the whole construction.
|
For more precise installation details of MASTERIMPACT® solid wall systems, please consult your local Intumex Asia Pacific organisation.
|
|